Aberdeen City Council roof replacements

Details
X

Get in touch

Head and shoulders image of John McHardy
John McHardy
Business Development Director - Tayside/Eastern Scotland
Send me an email

Summary

Sector
Affordable housing
Location
Aberdeen
Status
Completed
Customer
Aberdeen City Council
Completion
November 2025
Get social and share

45 homes improved and upgraded

Delivering safer, warmer and more resilient homes for residents, this phased housing refurbishment programme saw 45 roofs replaced and upgraded across Sheddocksley for Aberdeen City Council. 

Through early planning, tenant liaison, innovative methodologies, and proactive logistics, Robertson ensured time and cost savings, resident safety, and positive community engagement. 

45

Roof replacements

Live

occupied homes

Ahead

of schedule

Safe working in live residential environments

Resident and stakeholder safety was maintained throughout the project despite the challenges of working in occupied homes and managing complex site logistics. The key challenge was co-ordinating works while minimising disruption to residents. Through early tenant liaison, structured communication and daily engagement on site, residents were kept informed and reassured throughout. Just-in-time deliveries, sensitive landscaping considerations and proactive issue resolution helped accelerate progress and maintain a positive resident experience. 

Improving the quality of housing across the Sheddocksley area 

This project involved replacing existing roof tiles or slates for 45 properties. Works included full roof covering renewal including tiled and slate roofs, minor extensions to eaves, fascias and soffits to support future external wall insulation, and replacement of membranes, battens and counter-battens, along with any required sarking, truss and chimney repairs.  

Due to the dispersed nature of the properties, we set up a centralised compound with storage and welfare facilities. The methodology was refined to enhance safety, moving away from cantilevered scaffold removal in favour of dismantling the roof from within the roof structure. 

Image
roof on a red rendered house

Ahead of schedule for Aberdeen City Council residents

Efficient planning and increased resourcing brought the project ahead of programme. Finishing before Christmas was a key priority for ACC, ensuring scaffolding was removed from residents’ homes over the holiday period and avoiding unnecessary standing time. This early completion reduced disruption and delivered clear time and cost benefits. 

Added value for the economy and people of Aberdeen

Alongside improving the homes, the project delivered significant social and economic value for the local community. Our commitment to supporting local people, businesses and communities is reflected in the project's strong social value outcomes:  

  • 95% local labour within 10 miles 
  • 95% local labour within 20 miles 
  • 100% local labour within 40 miles 
  • 99% local spend within 40 miles 
  • 99% fair payment 
  • 100% Engagement with SMEs 

Route to market

The Aberdeen City Council project was directly procured through the Procurement Hub Major Projects Framework 2 (MPF2). This provided a flexible route to procure different projects together, and established time and cost savings through a transparent and collaborative engagement process.