Image
Durham university accommodation

Refurbishment of Trevelyan College, Durham University

Details
X

Get in touch

Summary

Sector
Private rented / student accommodation
Value
£4.69m
Location
Durham
Status
Completed
Customer
Durham University
Completion
September 2025
Duration
40 weeks
Get social and share

Improved residential facilities for undergraduate and postgraduate students

Robertson Construction North-East has delivered a £4.5m refurbishment of Trevelyan College, blocks B, C & D, for Durham University. We have completed 86 bedrooms, 13 kitchens and pantries, 2 flats and 2 lounge areas. These new facilities were a welcome improvement to the college and have enhanced the college lifestyle that Trevelyan is able to offer. 

Site works

The works began in December last year with a full strip out of the existing rooms, including the removal of asbestos in plantrooms, risers, plant rooms and pantries. A large operation then commenced to remove and replace the heating, water and drainage under the ground floor and through the risers. 

The scope also included the replacement of all windows located in the blocks, as well as various structural repairs to the brickwork façade. Scaffolding was erected, windows were replaced, cavity fill was complete, and repointing done to ensure the stability of the existing brickwork. 

Upon reinstatement of the M&E we were then able to commence the bedroom fitouts, with new furniture being installed in all bedrooms, flats, pantries, kitchens and lounges. The project was then complete with new flooring, decoration, and signage to provide a modern finish. 

Building strong relationships

Robertson delivered the project under a design and build contract following the completion of the Durham University Chemistry Building refurbishment. The project team were able to work collaboratively with the facilities and estates team at Durham University to deliver the project, as well as engaging with the team at Trevelyan College to ensure operation of the live accommodation building was maintained throughout the project.  

Increased energy performance

The buildings energy performance was also improved due to the replacement of all windows and doors, thermal upgrades were also carried out on the building fabric with additional insulation. These improvements will reduce the overall running costs for the college while contributing to Durham University’s wider sustainability targets.

“It is great to be back on campus to deliver improved spaces that will both reduce running costs for Durham University and enhance student experience. We worked closely with project partners and the University to mitigate disturbance to campus life and keep students informed every step of the way as we delivered this high-quality refurbishment."
Neil Kennedy
Regional Managing Director, Robertson Construction North East