RAAC refurbishment failsafe supports

Bramhall High School RAAC refurbishment

Details
X

Get in touch

Summary

Sector
Education
Value
£ 2m
Location
Stockport
Status
Completed
Customer
Stockport Metropolitan Borough Council
Completion
March 2025
Duration
33 weeks
Get social and share

Bramhall High School RAAC refurbishment

Robertson Construction North West has carried out rebuilding works at Bramhall High School to strengthen or remove RAAC (reinforced autoclaved aerated concrete) panels from the building. 

The school has reopened after having to close parts of the main building in 2023 after RAAC was found, with students learning in temporary buildings since then.

2,600m2

timber supports

Vital works to ensure safety

Robertson managed the supply and installation of fail-safe timber supports for RAAC planks, as well as overseeing other contractors working on behalf of Stockport. The project was divided into three phases, with initial work focused on the dining hall, kitchens, library and science labs.

Procurement route

The project was procured through a new main contract direct awarded to Robertson, following the successful delivery of Romiley Theatre. 

Project funding

The UK Department for Education made funding available for 234 schools across the country to help rebuild to remove RAAC, with Stockport Council securing funding for Bramhall High School from this School Rebuilding Programme.