Robertson construction of school in Clackmannanshire

Timber frame for Redwell Primary School, Alloa

Details
X

Get in touch

Summary

Sector
Education
Value
£8.5 million (total construction cost)
Location
Alloa
Status
Completed
Customer
Clackmannanshire Council
Completion
August 2014
Get social and share

Timber structure helps two schools to become one

For Clackmannanshire Council, through the hub East Central Scotland partnership, Robertson Construction provided a new primary school and nursery to meet the client's needs for a positive, modern school building with a strong identity.

Combining the St John's and Claremont Schools into one purpose-built facility successfully addressed ongoing issues with the existing schools, including the fabric of the buildings, disability access, running costs, and suitability for future educational needs.

444 

pupils

80 

nursery children

18 

classrooms

A timber framed school

The main body of the building houses the games hall, nursery and dining hall, while three classroom wings extend outwards to create learning spaces. 

The primary structural frame is timber, with the exception of the two-storey steel-framed games hall. 

Quickly delivering a light, airtight timber structure

Robertson Timber Engineering manufactured, supplied and erected the school's structural timber frame. 

The timber engineering team worked to a tight schedule to make sure the build programme was concluded with a handover to the local authority before the start of the school year in 2014. 

Other challenges included integrating our timber frame with a traditional steel frame structure, which were succesfully overcome. 

Ensuring the structure's airtightness requirements were met, we worked with BSRIA to integrate the vapour control layer within the timber frame.

Saving time through off-site timber manufacture

Use of factory-insulated, pre-fabricated roof cassettes saved considerable time on site. Traditionally trussed areas were constructed on the ground and then lifted into place, which meant operatives were not working at height and in turn sped up the process. Both of the above solutions reduced the need for expensive fall-arrest systems and provided a safer working environment for site operatives.

"The school has become something that the community is really proud of and felt that they were part of all the way through. So it has been much more than just a building project - and that's fantastic."
David Leng
Head of Education (2014)
Robertson's input has been way beyond what we would have expected - it's been outstanding. The children have spoken very positively about their experience from day one. They felt that they had a say in what their school looked like. It was fantastic that they could come and look at the site at every opportunity and see the building grow.
Gillian Ward,
Deputy Head Teacher, Redwell Primary School (2014)
I think this is one of the most positive contracts I have worked on. We had a fantastic array of engagement, from nursery right through Primary 7. Every pupil was involved, and we had superb ideas from the project manager, Craig Smith - like building the Anderson shelters for the WWII project, and showing the little ones how insulation works, or how a bricklayer operates - it was a really rewarding experience. The whole process has been fantastic. Everything came together, and it became a real team effort. We knew what we wanted for Clackmannanshire: we wanted to deliver a really high-class primary school, and we've got it!
Eileen Turnbull,
Asset Manager, Clackmannanshire Council (2014)

Working in partnership

Delivering the project through the hub East Central Scotland partnership allowed the design to be developed with the client and supply chain prior to the contract award. This partnering approach was critical in mitigating challenges and risks before the start of construction.

David Leng says: "This was a great example of partnership working. There are schools being built all over Scotland at the moment; ... that there was planning done with the schools and Robertson, which meant that they could develop the learning together. There was a real sense of ownership between both ourselves and Robertson."

Explore routes to market
 

  • Main Contractor: Robertson Construction
  • Architect: Keppie Design
  • Civil & structural engineer: Blyth & Blyth
  • Building services: Wallace Whittle
  • CDMC: Kirk & Marsh
  • Contract type: Design and build (hub East Central Scotland)
  • BREEAM: Excellent